How many days prior to a large asbestos project must the abatement contractor notify the NYSDOL?

Prepare for the New York State Asbestos Investigator Exam. Study with comprehensive flashcards and multiple choice questions, complete with hints and detailed explanations. Ace your upcoming test!

For large asbestos projects, the abatement contractor must notify the New York State Department of Labor (NYSDOL) at least 10 calendar days before the project commences. This requirement is in place to ensure that the appropriate regulatory bodies are informed of potentially hazardous activities, allowing for necessary oversight and safeguarding public health.

The 10-day notification period is designed to provide sufficient time for regulatory review and for any inspections to be scheduled prior to the start of the work. This timeframe helps ensure that all safety protocols are understood and followed, as handling asbestos requires strict adherence to health and safety regulations to minimize risks to workers and the public.

Understanding this requirement is crucial for compliance, as failing to notify the NYSDOL within the designated time frame could result in penalties or the halting of the project until the proper notifications are made.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy